Key Milestones…

June 2025

Stakeholder Agreements

July 2025

Submit a Planning Application

July 2025

Submit for Approval to Demolish

September 2025

Contractor Selection Begins

December 2025

Planning Approval

December 2025

Appoint Building Contractor

January 2026

Reds Temporary Move Grounds

January 2026

Demolish Borough Park

March 2026

Construction Works Commence

May 2027

Construction Complete

June 2027

Fit Out Complete

July 2027

Stadium Opens to Reds and Town

August 2027

Cumberland Sports Village Operates